Palm JumeirahAED 3,625/sqftCity WalkAED 3,268/sqftDubai Maritime CityAED 3,078/sqftDowntown DubaiAED 2,953/sqftDubai MarinaAED 2,836/sqftDubai IslandsAED 2,748/sqftBusiness BayAED 2,620/sqftDubai Creek HarbourAED 2,588/sqftDubai Hills EstateAED 2,444/sqftJumeirah Lakes TowersAED 2,229/sqftMohammed Bin Rashid CityAED 2,097/sqftAl JaddafAED 2,051/sqftJumeirah Village TriangleAED 1,673/sqftDubai SouthAED 1,630/sqftArjanAED 1,608/sqftJumeirah Village CircleAED 1,511/sqftDubai Sports CityAED 1,336/sqftPalm JumeirahAED 3,625/sqftCity WalkAED 3,268/sqftDubai Maritime CityAED 3,078/sqftDowntown DubaiAED 2,953/sqftDubai MarinaAED 2,836/sqftDubai IslandsAED 2,748/sqftBusiness BayAED 2,620/sqftDubai Creek HarbourAED 2,588/sqftDubai Hills EstateAED 2,444/sqftJumeirah Lakes TowersAED 2,229/sqftMohammed Bin Rashid CityAED 2,097/sqftAl JaddafAED 2,051/sqftJumeirah Village TriangleAED 1,673/sqftDubai SouthAED 1,630/sqftArjanAED 1,608/sqftJumeirah Village CircleAED 1,511/sqftDubai Sports CityAED 1,336/sqft
DLD · MEDIAN 12M TO JUL 2026

Dubai Land Department register

The Pulse Boulevard Grove

On holdDubai South Residential DistrictCompletion on file Sep 2019 — date passed

108 homes on the DLD register in Madinat Al Mataar, filed by DUBAI SOUTH PROPERTIES DWC LLC. No sale has been registered against it between 28 Apr 2025 and 6 Aug 2026.

Construction completeOn hold

As recorded by DLD's project register at 15 Jun 2026. An inspector's last visit, so it lags the site.

Developer entityDUBAI SOUTH PROPERTIES DWC LLC
Area (DLD)Madinat Al Mataar
StatusOn hold
Homes108
Registered sales0
Project registry

WHAT DLD HAS ON RECORD

Registry as at 15 Jun 2026
Registered developer entityDUBAI SOUTH PROPERTIES DWC LLC
Area (DLD)Madinat Al Mataar
Master communityDubai South Residential District
Project statusOn hold
Construction progress0.00% complete
Homes registered108
Buildings1
Registered start1 Jul 2017
Registered completion date1 Sep 2019
DLD project number1885
Description as recorded by DLD

One building composed as followed: Basement (parking and services) + Ground floor Parking and Services + 11 Apartments floors 1 pool deck on the podium level 1 gym and changing room on podium level 1 kid?s play room on podium level

Reproduced from the register verbatim, including its own abbreviations. It is the developer’s filed description, not our assessment of the project.

Source: Dubai Land Department project register, as recorded at 15 Jun 2026. “Registered completion date” is the completion date on file at DLD; it is a date on record, not a guarantee of handover, and where that date has already passed it means only that the register has not been updated, not that the project handed over. DLD does not publish a cancelled status for projects. Homes counted as registered apartments plus registered villas. Figures on this panel are the registry’s, and are stated as at a different date from the transaction figures elsewhere on the page. Registered completion: Sep 2019.

Registered sales

NO REGISTERED SALES IN THE PUBLISHED WINDOW

The Dubai Land Department transaction register we hold covers 28 Apr 2025 to 6 Aug 2026. No sale in this project was registered inside that window. That is not evidence that nothing has sold: the register is a backfill from 28 Apr 2025 onwards, so units sold before that date do not appear, and off-plan sales are registered on a lag. We publish no median, no trend and no price guide for this project, because we have nothing to base one on.

Transaction data as at 6 Aug 2026. Project facts as recorded by DLD at 15 Jun 2026 — a separate feed on a separate cadence.

Next step

ASK US ABOUT The Pulse Boulevard Grove

This page is the public register. What it cannot tell you is what is available now, at what price, on what payment terms, and how the specific unit compares with the ones already registered. Tell us your budget and objective and we will come back with the current position.