Payment plans Samana publishes
Samana's page sets out two plans. Under the post-dated-cheque plan the buyer pays 10 per cent down, then 1 per cent a month for 80 months, plus 5 per cent at month 6 and 5 per cent at month 12. Under the plan without post-dated cheques the buyer pays 15 per cent down, then 1 per cent a month for 75 months, plus 5 per cent at month 6 and 5 per cent at month 12.
Register schedule
The Dubai Land Department register, from a load dated 1 November 2026, gives project 4518 a start date of 1 August 2026 and an end date of 30 June 2029, for one building of ground plus six floors and a roof with 137 units. It names Emirates NBD as the escrow agent.
Location and travel times
Samana's page places the project in Dubai Industrial City and lists these destinations within a 15 to 20 minute travel band: Al Maktoum International Airport, Expo City Dubai, Ibn Battuta Mall, Dubai Investment Park, Dubai Marina, Legoland Dubai and Dubai Parks and Resorts, and Jebel Ali. These are the developer's estimates and will vary with traffic.
Market context
On 28 November 2026, the Dubai Land Department area that includes this project held 23 registered development projects with 3,912 units (Dubai Land Department). See every registered project in the area.
New residential leases registered through Ejari in the same area between 27 November 2025 and 26 November 2026 had a median annual rent of AED 50,000 for apartments (563 leases) and AED 78,000 for villas (69 leases), per Dubai Land Department data. The medians cover every building and unit size in the area.
The register records Samana Platinum Real Estate Development L.L.C as the registered developer of 7 projects holding 1,496 units in total, as at 28 November 2026, per Dubai Land Department data. See its projects on the register.
Per the DLD register, as at 28 November 2026, 18 projects in the same area that are not yet completed carry a registered completion date between 2026 and 2030:
| Registered completion year |
Projects |
| 2026 |
1 |
| 2027 |
5 |
| 2028 |
8 |
| 2029 |
4 |
| 2030 |
0 |
Registered completion dates are the dates developers have filed with the Dubai Land Department; developers can re-file them.
Enquire about South Haven 2
Mitchell's Commercial Real Estate acts for buyers in Dubai. To discuss South Haven 2, please contact us. Our buying costs calculator sets out the fees on a purchase.