Auresta Tower in Jumeirah Village Circle, by Tiger Properties
Auresta Tower is a single high-rise in JVC District 11, a neighbourhood of Jumeirah Village Circle (JVC), Dubai. It is a mixed-use building: apartments and duplexes above, with retail at ground level.
The building and units
The register describes the tower as three basement levels, a ground floor, four parking levels, five office levels and 55 residential floors. Three technical floors sit at levels 16, 35 and 51. The tower is designed to reach 255 metres (837 feet).
The unit types are studios, one-, two- and three-bedroom apartments and duplexes; the scheme is planned to include four duplexes.
The building is planned with these shared facilities:
- 24-hour security
- a swimming pool and a separate pool for children
- a fitness centre, sports courts, and space for yoga and meditation
- a sauna and a steam room
- a lounge area
- a garden and a play area for children
- jogging and bicycle paths
- retail outlets
The interiors are planned with marble in several varieties, decorative wall finishes and bronze detailing, plus smart climate control and sound insulation.
Location
Nakheel launched JVC in 2005 as a freehold master-planned community. Al Khail Road runs close by, and road connections link the community with Hessa Street.
Several fixed places are close to the tower:
- Circle Mall, where Roxy Cinemas operates, 0.3 km away
- parks: 0.4 km to Eirasha Park, 0.5 km to Gadaf Park and 0.6 km to the sports park in JVC District 16
- schools: 1.2 km to JSS International School and 1.3 km to Nord Anglia International School in Al Barsha
- 2.9 km to Dubai Miracle Garden
- 3.5 km to The Els Golf Club
- 5.7 km to Ski Dubai, and the same to the cinema in Mall of the Emirates
Among the neighbouring communities, Victory Heights lies 3.1 km away, Motor City and Sports City are each 3.4 km away, and The Springs is 3.7 km away.
DLD register status
The Dubai Land Department register, read 7 November 2026, holds Auresta Tower as project 3734, status active and labelled under construction.
- Percentage complete: 4.44%, as at 8 October 2026
- Start date: 1 May 2025
- Projected completion: 31 December 2028
- Escrow agent: First Abu Dhabi Bank P.J.S.C.
Completion is the date projected in the register, not a handover commitment.