Palm JumeirahAED 3,625/sqftCity WalkAED 3,268/sqftDubai Maritime CityAED 3,078/sqftDowntown DubaiAED 2,953/sqftDubai MarinaAED 2,836/sqftDubai IslandsAED 2,748/sqftBusiness BayAED 2,620/sqftDubai Creek HarbourAED 2,588/sqftDubai Hills EstateAED 2,444/sqftJumeirah Lakes TowersAED 2,229/sqftMohammed Bin Rashid CityAED 2,097/sqftAl JaddafAED 2,051/sqftJumeirah Village TriangleAED 1,673/sqftDubai SouthAED 1,630/sqftArjanAED 1,608/sqftJumeirah Village CircleAED 1,511/sqftDubai Sports CityAED 1,336/sqftPalm JumeirahAED 3,625/sqftCity WalkAED 3,268/sqftDubai Maritime CityAED 3,078/sqftDowntown DubaiAED 2,953/sqftDubai MarinaAED 2,836/sqftDubai IslandsAED 2,748/sqftBusiness BayAED 2,620/sqftDubai Creek HarbourAED 2,588/sqftDubai Hills EstateAED 2,444/sqftJumeirah Lakes TowersAED 2,229/sqftMohammed Bin Rashid CityAED 2,097/sqftAl JaddafAED 2,051/sqftJumeirah Village TriangleAED 1,673/sqftDubai SouthAED 1,630/sqftArjanAED 1,608/sqftJumeirah Village CircleAED 1,511/sqftDubai Sports CityAED 1,336/sqft
DLD · MEDIAN 12M TO JUL 2026

Dubai Land Department register

The Community Motor City

Under constructionMotor CityCompletion on file Oct 2025 — date passed

433 homes on the DLD register in Al Hebiah First, filed by Aqua Properties FZ -LLC. 43 sales have been registered against it between 28 Apr 2025 and 6 Aug 2026.

Construction completeUnder construction

As recorded by DLD's project register at 15 Jun 2026. An inspector's last visit, so it lags the site.

Developer entityAqua Properties FZ -LLC
Area (DLD)Al Hebiah First
StatusUnder construction
Homes433
Registered sales43
Project registry

WHAT DLD HAS ON RECORD

Registry as at 15 Jun 2026
Registered developer entityAqua Properties FZ -LLC
Area (DLD)Al Hebiah First
Master communityMotor City
Project statusUnder construction
Construction progress50.02% complete
Homes registered433
Buildings1
Registered start1 Nov 2022
Registered completion date31 Oct 2025
DLD project number2532
Description as recorded by DLD

G+P+6+R Residential+Retail.The project designed to have a concrete structure and block with internal and external finishes.

Reproduced from the register verbatim, including its own abbreviations. It is the developer’s filed description, not our assessment of the project.

Source: Dubai Land Department project register, as recorded at 15 Jun 2026. “Registered completion date” is the completion date on file at DLD; it is a date on record, not a guarantee of handover, and where that date has already passed it means only that the register has not been updated, not that the project handed over. DLD does not publish a cancelled status for projects. Homes counted as registered apartments plus registered villas. Figures on this panel are the registry’s, and are stated as at a different date from the transaction figures elsewhere on the page. Registered completion: Oct 2025.

Registered sales

WHAT HAS ACTUALLY BEEN PAID HERE

DLD register · as at 6 Aug 2026

43 sales were registered against The Community Motor City between 29 Apr 2025 and 28 Jun 2026 — a span of 14 months. Those are completed registrations at the Dubai Land Department, not asking prices or listings.

Median AED/sqft
1,386
Across 43 registered sales
Median price
AED 750k
Median size 523 sqft
Registered sales
43
28 Apr 2025 to 6 Aug 2026
Vs area median
-28.2%
Al Hebiah First: 1,930 AED/sqft, 2,286 sales, off-plan only, 12 months to 6 Aug 2026

The two figures behind that percentage are not drawn on the same population. This project’s median covers every registration type across the whole register we hold (28 Apr 2025 to 6 Aug 2026). The area figure covers off-plan only in Al Hebiah First over the 12 months to 6 Aug 2026, pooled on the transaction register’s own area name, which does not always match the project register’s name shown above. Unit mix, floor level, view and use class are not controlled for on either side. Read it as an indication of where this project sits in its area, not as a like-for-like comparison.

Median AED/sqft by quarter

No quarter in the window reached 20 registered sales, which is the minimum we require before plotting a point or quoting a change. Drawing a line through thinner quarters would turn a handful of deals into a trend.

By unit size
TypeSalesMedian sizeMedian AED/sqft
Studio24433 sqft1,473
1 bedroom15681 sqft1,243
2 bedrooms1
3 bedrooms3

A median is shown only where the band reached 5 registered sales and the project itself cleared the 10-sale floor; otherwise the count stands on its own and the median is left blank. Where a project is below that floor, a band median would be the project median under a different heading.

First sale vs resale
Registration typeSalesMedian AED/sqft
Off-plan (first sale from developer)431,386
Existing (resale)0

DLD splits registrations into off-plan and existing. The two are not directly comparable: an off-plan registration is a launch-price contract, an existing registration is a completed unit changing hands. Where both appear, the gap between them reflects that difference as much as any movement in value. A median is shown on each side only where the band reached 5 registered sales and the project itself cleared the 10-sale floor — below that floor the counts stand alone, because where every sale falls on one side its median is the project median restated.

Buildings in the register
BuildingSales
The Community Motor City28
The last 12 registrations to 6 Aug 2026
DateTypeUnitSizePriceAED/sqft
28 Jun 2026Off-planStudio433 sqftAED 620,0001,432
22 Jun 2026Off-planStudio559 sqftAED 826,0001,479
16 Jun 2026Off-plan1 bedroom677 sqftAED 885,0001,308
19 May 2026Off-plan3 bedrooms1,825 sqftAED 2,130,0001,167
8 May 2026Off-plan1 bedroom797 sqftAED 935,0001,174
1 May 2026Off-plan1 bedroom1,003 sqftAED 980,000977
24 Apr 2026Off-plan1 bedroom681 sqftAED 899,8881,322
22 Apr 2026Off-planStudio565 sqftAED 560,000991
9 Apr 2026Off-planStudio418 sqftAED 750,0001,795
2 Mar 2026Off-plan1 bedroom768 sqftAED 849,8881,106
27 Feb 2026Off-plan1 bedroom768 sqftAED 849,8881,106
26 Feb 2026Off-plan2 bedrooms1,202 sqftAED 1,433,8701,193

Basis: Dubai Land Department transaction register, arm’s-length sales of units and villas only. Gifts, mortgage registrations, zero-price rows, land plots and whole-building transfers are excluded, as are AED/sqft values outside 10020,000. Figures are medians, not averages. The register we hold runs from 28 Apr 2025 to 6 Aug 2026; 28 Apr 2025 is the earliest date in our copy of the register, not the date this project started selling, so the counts above are of sales registered in that window rather than since launch. This page is a dated extract taken on 7 Aug 2026, not a live query. Past registered prices are evidence of what has been paid, not a forecast of future value.

Location

WHAT THE REGISTER RECORDS NEARBY

Nearest metroDubai Internet City
Nearest mallMall of the Emirates
Nearest landmarkMotor City

These are the values DLD records against this project’s own registered sales, not a distance we measured. Where a project’s sales disagree, the most frequently recorded value is shown.

Next step

ASK US ABOUT The Community Motor City

This page is the public register. What it cannot tell you is what is available now, at what price, on what payment terms, and how the specific unit compares with the ones already registered. Tell us your budget and objective and we will come back with the current position.

Need help?